New York Independent System Operator / McKean County
Stargazer I and II in New York’s interconnection queue
RWE Solar Development, LLC filed two requests on September 17, 2024. The queue places both generating sites in Pennsylvania. For both, RWE is seeking access to the grid that serves the New York wholesale electricity market.
Read the two rows
Open the Cluster Projects worksheet, rows 47 and 48. Both name McKean County, PA, a 345 kV point of interconnection on the Homer City to Pierce Brook line, and the utility NYSEG (New York State Electric & Gas). The workbook classifies each as a proposed co-located storage resource.
Each row lists 325 MW in summer and winter. Each proposes January 2029 for initial backfeed, February 2029 for synchronization and July 2029 for commercial operation. The workbook is dated August 31, 2026. The individual rows show June 30, 2026 as their last update.
Download the complete NYISO queue (.xlsx) →Where the 170 MW comes from
Slide 38 of NYISO’s March 26, 2026 study lists 325 MW of requested Energy Resource Interconnection Service and 325 MW of requested Capacity Resource Interconnection Service (CRIS) for each project. Those are two kinds of service for the same resource. Slide 41 breaks each project’s capacity request down by technology.
| Queue entry | Solar | Battery | Total |
|---|---|---|---|
| C24-175 | 240 | 85 | 325 |
| C24-176 | 240 | 85 | 325 |
| Combined | 480 | 170 | 650 |
The 480 MW of requested solar capacity matches RWE’s Pennsylvania application. The 170 MW describes the rate at which the two batteries would discharge. Adding solar and battery capacity does not turn stored energy into additional solar generation.
Read the line and service entries on slide 38 →
Read the solar and battery notes on slide 41 →
NYISO, Transition Cluster Study 2024, Preliminary Deliverability Study, March 26, 2026. The two slides appear on PDF pages 39 and 42 of Appendix 21-A in New York Department of Public Service Matter 24-03063. Little Salmon Solar filed that appendix for its own project. NYISO’s study covers the whole cluster, including Stargazer I and II.
What Pennsylvania residents were told
RWE’s Sergeant Township application describes a proposed 480-megawatt (AC) solar facility with battery storage on approximately 3,515 acres. Its project narrative refers to the Stolle Road to Homer City Station 345 kV line. The NYISO workbook uses the Homer City to Pierce Brook line name. RWE can identify the exact connection point on its latest engineering plan.
The application compares estimated annual output with the electricity used by more than 77,000 average U.S. homes. Neither the application’s comparison nor the NYISO entries identify a buyer, a guaranteed local bill credit or a contract scheduling delivery to New York customers. July 2029 describes when RWE proposes to operate.
Read RWE’s application and generation estimate, PDF pages 2–3 →