McKean County, Pennsylvania
Stargazer Solar’s 21 receiving waters
The January 2026 stormwater report and the Chapter 102 meeting form list the same 21 streams, hollows and numbered tributaries. Use this page to find each waterway’s Pennsylvania protected use and see what DEP reported for the reaches we could match.
Read the stormwater report · See the DEP meeting form · Download the table (CSV)
Protected use
HQ-CWF means High Quality–Cold Water Fishes. CWF means Cold Water Fishes. The classification identifies which uses and protections Pennsylvania applies to a stream or reach.
Condition DEP mapped
The assessment column describes individual uses on matched reaches in DEP’s October 2026 layers. A reach can support aquatic life and still have an impairment for recreation or fish consumption.
Protected uses and DEP assessments
The DEP assessment column shows conditions for the mapped reaches we could match.
Stormwater report, p. 3DEP meeting form, p. 1
Showing 21 of 21 receiving waters
No streams match. Try another name or code.
| Stream or tributary | PA water quality classification | DEP’s mapped assessment |
|---|---|---|
| Marvin Creek drainage | ||
| Marvin Creek | HQ-CWF / CWFThe July 2026 state rule designates the basin from the source to Kane Creek HQ-CWF. Downstream main-stem reaches are designated CWF. DEP also maps HQ-CWF existing-use protection on portions of Marvin Creek. A dated outfall location is needed to assign the specific reach. |
|
| Warner Brook | HQ-CWFHQ-CWF for the basin under § 93.9p. |
|
| Jet Brook | HQ-CWFTributary in the Warner Brook basin. |
|
| Stone Dock Hollow | HQ-CWFTributary in the Warner Brook basin. |
|
| Tributary 57785 to Warner Brook | HQ-CWF |
|
| Bloomster Hollow | CWFMapped as CWF in the Marvin Creek drainage. |
|
| Shelander Hollow | CWFThe application lists one hollow. DEP’s legacy layer uses the name for two channels that feed Bloomster Hollow. |
|
| Tributary 57768 to Bloomster Hollow | CWF |
|
| Irons Hollow | CWFMapped as CWF in the lower Marvin Creek drainage. |
|
| Tributary 57756 to Irons Hollow | CWF |
|
| Potato Creek and Red Mill Brook drainages | ||
| Robbins Brook | HQ-CWFHQ-CWF for the basin under § 93.9p. |
|
| Donley Fork | HQ-CWFTributary within the Robbins Brook basin. |
|
| Boyer Brook | HQ-CWFHQ-CWF for the basin under § 93.9p. |
|
| Wernwag Hollow | HQ-CWFListed in § 93.9p as UNT 57891 in the Red Mill Brook basin. |
|
| Browns Mill Hollow | CWFMatched to the Cold Water Fishes reaches in the Red Mill Brook basin. |
|
| Tributary 57887 to Red Mill Brook | CWFLegacy channel joins tributary 57886 in the Red Mill Brook drainage. |
|
| Tributary 57886 to Red Mill Brook | CWF |
|
| Tributary 57885 to Red Mill Brook | CWF |
|
| Tributary 57884 to Red Mill Brook | CWF |
|
| East Branch Clarion River drainage | ||
| Martin Run | HQ-CWFIn the East Branch Clarion River basin under Drainage List R (§ 93.9r). |
|
| Tributary 50849 to Martin Run | HQ-CWF |
|
What stands out in the assessment
- Robbins Brook is designated HQ-CWF. The matched reaches support aquatic life and recreation. Pennsylvania Fish and Boat Commission lists it as a wild trout water. See the commission’s trout reproduction list.
- Marvin Creek, Warner Brook and Bloomster Hollow have reaches where DEP lists recreation impairment for pathogens from an unknown source. Irons Hollow also has mapped aquatic-life impairment for nutrients and siltation from an unknown source.
- Martin Run and tributary 50849 support aquatic life on matched reaches. DEP also maps a fish-consumption impairment for mercury from atmospheric deposition.
These assessments describe mapped stream conditions and the causes listed by DEP. The reviewed sources do not attribute these impairments to Stargazer. Determining suitability for drinking or livestock watering requires site-specific sampling.
DEP attaining assessment layer · DEP impairment layer, including listed causes
What the project records establish
January 20 stormwater report. Kimley-Horn says 26 modeled drainage points ultimately convey to these 21 waters. It says the site design would keep the relative drainage patterns, generate more runoff from added impervious area, and use proposed infiltration basins to reduce peak rates and control volume. Read the report’s drainage analysis · View the overall stormwater plan
August 18 and September 17 pre-application records. The August receipt records “No” for the broad question about construction-related or clean stormwater discharge. The Chapter 102 meeting form circulated September 17 marks “Yes” for proposed stormwater discharges to High Quality or Exceptional Value surface waters. It checks CWF and HQ, leaves the EV classification box unchecked, and marks that at least one listed impairment concern applies to receiving waters. DEP’s reach assessments give the separate findings shown above. Read the original wording side by side
September 9 DEP correspondence. DEP’s Northwest Region permits chief, Karl M. Gross, wrote, “It will require an Individual NPDES and probably 105.” That was staff correspondence at the pre-application stage. The records reviewed refer to draft post-construction plans and include an overall drawing. An issued stormwater authorization and a final outfall schedule remain unverified. Read the released excerpt · DEP’s public permit and license tracker
For downstream neighbors. Ask for the dated plan that identifies the individual discharge locations, receiving reaches and stream crossings. That is what can connect a project feature to a specific point on a brook.
Sources and how the reaches were matched
- The 21 rows follow the names in the Chapter 102 form and the January 2026 stormwater report. Names and five-digit codes were matched through DEP’s Historic Streams layer, then traced against mapped reaches in the October 2026 layers. The downloadable source data includes legacy codes and DEP reach IDs, called COMIDs.
- Protected uses come from Pennsylvania’s Drainage List P (§ 93.9p) and Drainage List R (§ 93.9r), checked against the designated-use layer and existing-use layer. The July 2026 final rule raised the Marvin Creek basin from the source to Kane Creek to HQ-CWF. The legal designation in that rule is used here where the older map coding differs.
- Assessment findings come from the October 2026 attaining and nonattaining layers published by DEP through PASDA. DEP’s 2026 Integrated Water Quality Report page hosts the draft report and explains its assessment process. We report only findings on matched reaches. Uses without a match stay blank in the download.
Download all 21 rows as CSV · Download the reach matches as JSON