Messages released by Pennsylvania DEP describe the Stargazer pre-application process and the questions the project raised about streams, wetlands and stormwater.
Transcribed from the released Outlook files. The August entry includes the receipt’s explanation and questions 32 and 51. The other entries reproduce each sender’s message through the sign-off. Sender contact blocks, email security banners and repeated thread history are omitted. Each entry links to its source file.
DEP automated questionnaire receipt
Pennsylvania Department of Environmental Protection
Subject DEP Permit Application Consultation Tool (PACT) submittal for project name: Stargazer Solar
Thank you for using the DEP Permit Application Consultation Tool (PACT) submittal. Your project information has been received by the Department of Environmental Protection. Based on your answers to the PACT questionnaire, the tool has provided the attached responses highlighting important considerations related to your project. These responses are based solely on the project information you provided, and may not be comprehensive, but will serve as a starting point for the conference.
Question 32 Does the project involve any of the following: placement of fill, excavation within or placement of a structure, located in, along, across or projecting into a watercourse, floodway or body of water (including wetlands)? No
Question 51 Will the project involve discharge of construction related or clean stormwater to a dry swale, surface water, ground water or an existing sanitary sewer system or separate storm water system? No
Permits Chief, Waterways and Wetlands · Pennsylvania DEP Northwest Regional Office
It will require an Individual NPDES and probably 105.
Excerpt from released Stargazer pre-application correspondence in DEP RTKL 2026-1754. NPDES here refers to the stormwater discharge permit. Chapter 105 covers water obstructions and encroachments. The email records the staff member’s expectation before an application decision.
Tyler J. Bintrim
U.S. Army Corps of Engineers, Pittsburgh District
Subject [External] RE: DEP Permit Application Consultation Tool (PACT) submittal for project name: Stargazer Solar
Staci,
Sounds like no impacts to streams or wetlands. That’s pretty impressive considering the size of this solar project.
Pennsylvania Department of Environmental Protection · Permits Chief
Attachments Chapter 102 meeting form and overall project map
The project description/narratives usually indicate the generating capacity of the project. Here’s what was presented for the PACT meeting for a project in McKean County.
Assistant Regional Director, PA DEP Northwest Regional Office
Subject FW: [External] Voice Mail (1 minute and 1 second)
Karl,
I will be out of the office until Wednesday next week, but I think we should hear Sandy’s concerns. I don’t necessarily need to be part of that, and I think you and Eric can call her in my absence.
Eric,
This is a 3500+ acre solar project, likely the largest project of its kind in the Commonwealth.
We held a pre-application meeting on Monday, September 14th. (See attached PACT information.)
I reached out to Bob Jevin last week and asked him to consider handling this under Major Projects. I have not heard back from Bob, but I will nudge him next week.
I may set up a call with Kevin White (Bob’s supervisor) and Bob later next week if we can’t get a decision.
District Manager, McKean County Conservation District
Subject [External] RE: DEP Permit Application Consultation Tool (PACT) submittal for project name: Stargazer Solar
Good Morning,
I would like to propose holding a meeting amongst all of us just to summarize everything that was discussed and presented during the meeting. I’m sure you all understand the concern we have for this project especially with the amount of disturbance for this project and the potential environmental impact. I have reached out to the consulting forester for Manulife asking if we could visit the site to gain a better understanding of the site. If any of you would be interested in attending when we get a site visit scheduled, please let me know.
Let me know your thoughts of scheduling a meeting for further discussion on this project.
Subject [External] RE: DEP Permit Application Consultation Tool (PACT) submittal for project name: Stargazer Solar
Sandy,
Pittsburgh Corps may be interested in a site visit. I’m not sure how a 3,500 acre site doesn’t impact a stream or wetland anywhere. I know the solar companies usually try to avoid streams and wetlands but this one is huge.
District Manager, McKean County Conservation District
Subject [External] RE: Stargazer Solar Project Tour
Hi Everyone,
We have scheduled the tour of the proposed Stargazer Solar project for October 30th. We will plan to meet at our office at the address listed below at 10:00 AM and then carpool to the site.
Please RSVP by October 26, if you are planning to attend.